Hello Experts,
Could any one tell me what is the integration part between CO & PP?
Regads,
Comments
For PP-CO intergration the following parameters which are defined in the order dependent parameters are required:
1) Costing variant - planned and actual.2) Costing sheet3) RA key - This is for WIP calculationThe customiation of the above parameters are done in Controlling by the CO person.
Following are the imp ones:
Costing variant: Transaction OPL1
Key that specifies which costing variant is used to determine the planned costs.
The costing variant refers to a valuation variant. Transaction - OPN2
The valuation variant
2) Costing sheet - Transaction - Under overheads in Prod cost Planning in CO.
3) RA key: <b>Trans: OKG1</b> - specify the RA key.
- Define cost element
- Define RA version - OKG9
- Define assignment - OKGB
4) Create settlement profile - under period end closeing in customization.
Regards
Ganesh 7619187537
For PP-CO intergration the following parameters which are defined in the order dependent parameters are required:
1) Costing variant - planned and actual.
2) Costing sheet
3) RA key - This is for WIP calculation
The customiation of the above parameters are done in Controlling by the CO person.
Following are the imp ones:
Costing variant: Transaction OPL1
Key that specifies which costing variant is used to determine the planned costs.
The costing variant refers to a valuation variant. Transaction - OPN2
The valuation variant
2) Costing sheet - Transaction - Under overheads in Prod cost Planning in CO.
3) RA key: <b>Trans: OKG1</b> - specify the RA key.
- Define cost element
- Define RA version - OKG9
- Define assignment - OKGB
4) Create settlement profile - under period end closeing in customization.
Regards
Ganesh 7619187537