If you want your auto goods receipt or good issues that will further result in saving in the manual interference and in so doing the cost using an instinctive process in the respective system you have to use a process which is known as backflushing, for this you have to activate with in the operation overview work center and material master. 

Please make sure that material master will have a higher priority. If you want goods to be operated in a proper process you would have to activate the backflush automatically. Moreover you would be able to activate the backflush directly to process the order.

Backflushing is basically a robotically goods issue, as soon as you confirm the operations your system will repeatedly posts the goods issue. Please make sure that it will automatically reduce the effort you not ought to make manual issue. Backlushing is unconscious accounting of material spent for production as soon as all changes are confirmed. Basically backlush is used where it is having a fixed relationship. Next you can also configure it in MRP2 screen, work center or routing or in production order. 

Please make sure that everyone has some special function. You not need to activate this in MRP2 or work center screen, MRP2 screen will well defined the material components that are being backflushed. This comes under the environment of Production Planning.


Comments

  • 30 Aug 2011 12:06 pm raju Helpful Answer

    Hello balakrishnan, 

    Backflushing: A term used to describe the function of a component issue from stock, at the time of completing the works order. These parts are issued automatically from stock without user interaction. The quantity backflushed is dependant upon the bill of material usage.

    If having any problem please updated in this site.

    we will help u. 

    Regards 

    veera.

  • 12 May 2017 3:22 pm Romil Tripathi Helpful Answer

    Back flushing is nothing but automatic goods issue. System will automatically posts the goods issue when you confirm the operations.You have no need to make manual issue. It will reduce the effort.

    Backflushing is automatic accounting (Goods issues - 261 mvt) of material consumed for production, at the time of confirmation. Eg. When a 4 wheeler automobile is rolled out from assy line, 4 wheels & Tyres are deemed to be consumed and issued to production order automatically by way of backflushing by the system.

    Assy line picks the material from stores/ Assy line and use.

    No Physical issue & Manual posting ( Goods Issue) by Stores.

    Backflush is used for material which are a must and having fixed relationship.

    This can be configured in MRP2 Screen,Work centre, Routing and production order.

    Each has some special function.

    If you configure this in routing or production order you have no need to activate this in MRP2 or Work center screen.

    MRP2 Screen defines whether material components are backflushed are to be made at the work center.

    When we do the back flush the backlogs are being created for the BOM components and we are getting the message "Backlogs from backflush were created or changed" - its just an informative message. Do you think this has got something to do with the negative postings ?

    Backlogs are created due to different reasons.

    This message tells that "there is no sufficient stocks for the bom component/not able to backflush all the material due to plant data locked etc" at the time of backflushing the BOM Material and hence the Post-processing list is created that you have to Re-process for stock updation of each material.

    To avoid this you can confirm the following things.

    1.Ensure that suffecicient stock is available in the backflushing locations of each materail.

    2.To prevent the generation of "post-processing list" you can block the BOM from getting backflushed if sufficient stock is not available in specified location for the BOM COMPONENTS. To do this change the "REM profile" to "002"in MRP4 view for the BOM MATERIAL.(if the profile is not available you can crate it through SPRO).

    3. To clear the existing Backlog use transcation MF47 and re-process(be ensure that required stocks is available for each bom component)


     

  • 07 May 2014 10:38 am Guest

    backflush is consuming the components to the production order automatically without individually posting .


×