Hi,
My requirement is
How to run the process chain first 8 working days of every month.
Can anyone recommend how to fulfill this requirement?
And where I have to write in process chains?
Thank you
You can view more tutorials about SAP BW
Updated May 18, 2018
Hi,
My requirement is
How to run the process chain first 8 working days of every month.
Can anyone recommend how to fulfill this requirement?
And where I have to write in process chains?
Thank you
You can view more tutorials about SAP BW
Comments
Suppose we need to run a Process chain first 8 days of every month.....
In this case..........Create a Factory Calendar using Tcode SCAL.......there declare first 8 days as Working days and rest all as Holidays.
Right click on the Start Process >> Display variant >> Change Selections >> Click on Date/Time tab >> Click on the Restriction tab (F6) >> there maintain the Calendar id and Select Do not Execute on Sundays or Holid.........>> Then Check and Transfer........... Then in the Scheduled start field give the date when the Chain is going to run for the first time............
Then the Process chain will only run as per the above requirement.