How to Transfer the Existing Asset one Cost Center to Another Cost Center?

Updated May 19, 2018

Hello Experts,

May I know that how to transfer the existing asset one cost center to another cost center?

Can any one please give me solution?

Thanks in advance.


Comments

  • 25 Aug 2017 3:29 pm Guest Best Answer

    Go to KB11N and put old cost center, Amount and new cost center. Click on post and cost will be transferred to new cost center. But before you do so you need to save new cost center in control data of asset master. You can use T-code AS02.

  • 14 Dec 2017 3:07 pm Shalesh Singh Visen Helpful Answer

    You can post a partial transfer (percentage or dollar amount) and transfer to different cost center. If it is set up, remember to use the Time Interval function.


×