I'm trying to uderstand the "Confirmation" feature of SAP. For example:
I cut a subcontracting PO for a finished good that consumes 100 units of component A on day 1
I have 110 units of component A in stock so when I check component availability I see that 100 units confirmed on day 1
then I cut a second subcontracting PO for the same FG material for 80 units on day 2. When I perform the availability check I see that 80 units confirmed on day 2.
Now I have confirmations for a total of 180 units but I only have 110 units in stock.
I was under the impression that once a confirmation is done the quantity and material are allocated to the order and is therefore no longer "available". But that is not what I see.
Is there a way to "hard allocate" units of a component to the order for the higher assemnbly in a ay that nets it out of available inventory?
Every consultant I talked to seems to not really understand what the system logic is.
Thanks
Andre Soares